Tai Hang Project

(Last Updated: January 2019)

- The foundation works have been completed.
- Waiting for the approval of superstructure works, and expected to start after Lunar New Year. 

 

Chatham Road North Project

(Last Updated: January 2019)

- Construction of RC structure of the tower is in progress, currently working on the 21st floor.
- Interior works of lower floors have been started.
- The main structure is expected to be finished before Chinese New Year; the construction is on schedule.
- DMC and Sale brochures have been finalized.
- Expected to obtain Occupation Permits (OP) in late 2019.
 

-----------------------------------------------------------------------------------------------------

Tai Hang Project

(Last Updated: July 2018)

- The piling work has been completed on early July, and in application for Certificate of Completion.
- The foundation works are in good progress, and will be completed within 5-6 months.
- Further amend the general building plan as to provide a better design.

 

Chatham Road North Project

(Last Updated: July 2018)

- The project is keeping work on good progress, and still about 2 months ahead of schedule.
- Submitted General Building Plan (GBP) 2nd  amendment to Building Department on 10th  July,  including the commercial signboard on 3rd floor.
- Modeling of surrounding environment completed.
- Preparing Combined Service model with all building services.
- Preparing documents for Deed of Mutual Covenant (DMC) and pre-sale Brochure.
- Pile cap work as an important milestone for ground works has completed; waiting for Certificate of Compliance from Lands Department.
- Another important milestone that the Consent of Superstructure Work has been obtained on 30th  May, 2018. Superstructure work has officially started on 13th  June, 2018.

 

-----------------------------------------------------------------------------------------------------

Tai Hang Project

(Last Updated: January 2018)